Newnan Crossing Bypass paving resumes today

From Staff Reports
news@newnan.com
The paving project on Newnan Crossing Bypass will resume today, Newnan city officials said.
Michael Klahr, city engineer, said Tuesday that, due to the weather, the contractor has revised his schedule to work from 9 a.m. to 9 p.m. and will resume work today on the Newnan Crossing Bypass Pavement Rehabilitation Project.
Until the southbound lanes for Newnan Crossing Bypass are complete, he will continue to cut down one left turn lane from Bullsboro Drive onto Newnan Crossing Bypass while his work progresses, Klahr said.
“Milling is complete as is paving with binder in the mainline,” Klahr reported. “The final lift of asphalt is being placed, with one lane completed Monday night.”

More Local

10 Things to Know for Today

Your daily look at late-breaking news, upcoming events and the stories that will be talked about today: 1. NETANYAHU SET FOR CONGRESS SPEECH ... Read More


Georgia to execute only woman on state's death row

ATLANTA (AP) — The only woman on Georgia's death row is set to be executed Monday. Kelly Renee Gissendaner, who's 46, is set to die at ... Read More


Programs reflect growing diversity in schools

Coweta County – like the rest of Georgia – is growing more diverse, and that is reflected in programs being held in the county&r ... Read More


Eye-catching billboard may help catch killer

When travelling on Interstate 85 north through Fairburn, many motorists have taken notice of Donna “Denice" Roberts’ face on a l ... Read More


Acceptance starts with liking one’s self

“Diversity – it starts with you.” That was the message that keynote speaker Nick Ferrante brought to the Diversity Day pro ... Read More